This project involved enclosing Company Canal to allow it to serve as a safe harbor during storm events and to provide a new line of hurricane protection to 100 year storm levels. Cajun’s scope of work included construction of a new sector gate and pump station together with their associated channels, construction of a T-wall type floodwall, and construction of a channel closure across Bayou Segnette. Also included in the scope of work was construction of a permanent section of earthen levee from the sector gate to the adjacent floodwall.
USACE-New Orleans District WBV-16.2 Bayou Segnette Complex
JEFFERSON, LA
JEFFERSON, LA
Statistics
- 43-month duration
- 223,652 man-hours
- 65 peak manpower
Work Performed
- Construction of a new sector gate structure in a marine environment
- Construction of temporary retaining structures (TRS) for the sector gate, pumping station and T-wall/channel closure structures including design of two of the TRSs
- Clearing and grubbing of the project site, which is in a low-lying, swampy area
- Placement of approximately 10,000 CY of reinforced concrete
- Channel excavation (dredging) of approximately 75,000 CY (including one navigable channel for the sector gate)
- Periodic maintenance dredging
- Construction of nine T-wall monoliths
- Embankment of approximately 58,000 CY of compacted fill for construction of an earthen levee
- Installation of over 42,000 SF of sheet piles
- Installation of a creosote treated timber pile fender system
- Installation of 24” and 30” pipe piles
- Construction of a guidewall using a floating plant
- Site unwatering and dewatering
- Installation of needles, a needle girder and a storage platform
- Demolition of an existing gate
- Construction of a 14’ earthen levee
- Clearing and grubbing of the project site, which was situated in a low lying area
- Placement of over 33,000 tons of 650LB rip rap from a barge
- Installation of scour protection
- Installation of operating machinery at the sector gate and pump station
- Installation of water craft protection dolphins in Company Canal and at the pump station
- Design and implementation of emergency gap closure and temporary flood protection plans to replace existing protection removed for construction access tie-ins with new protection