Tenaris Civil

BAY CITY, TX
BAY CITY, TX

Cajun was responsible for installing pipe piling & spread footing foundations for a new pipe mill building. As the general contractor, Cajun self-performed 75% of the work on this project.

Accomplishments

Cajun completed project two weeks ahead of schedule.

Statistics

  • 10 month duration
  • 63,672 man-hours
  • 160 peak manpower
  • 0.00 TRIR

Work Performed

  • Installed 11,698 CY of structural concrete
  • Installed 2,136 16” x 70’ pipe piles
  • Installed 50,000 CY of structural backfill
  • Installed 1,357 tons of reinforcing steel