This project consisted of the construction of a two-story 4,375 SF MCC/ Blower Building for Hexion’s G6 Gulfstream Project. Cajun Industries served as the General Contractor for the project.
Hexion G6 Blower Building
GEISMAR, LA
GEISMAR, LA
Statistics
- 11 month duration
- 2,267 man-hours
- 0.00 TRIR
Work Performed
- Masonry
- Access flooring
- Metal canopies
- Painting
- HVAC work
- Cast-in-place concrete
- Structural steel fabrication and erection
- Spray and injection foam insulation
- Fluid applied membrane roofing
- Hollow metal doors
- Overhead coiling doors