CLECO Power Sherwood to Donahue 230 kV Transmission Line

PINEVILLE, LA
PINEVILLE, LA

Cajun was contracted by CLECO Power to provide all supervision, labor, equipment, and material to install all foundations for the completion of a new 10 mile long 230 kV transmission line.

Accomplishments

  • Cajun safely and successfully installed all foundations overcoming many obstacles including rough terrain conditions, working in limited areas, exceeding schedule expectations among many others.

Work Performed

  • Provided access for all equipment and trucks.
  • Installed 115 drill shaft foundations ranging in diameter from 4’-9’ and ranging in depth from 18’-47’.

Statistics

  • 6-month duration
  • 11,305 man-hours
  • 26 peak manpower