CLECO Red Bayou Susbstation

PELICAN, LA
PELICAN, LA

Cajun was contracted to drill and pour 170 EA drill shaft foundations for a new substation in north Louisiana.

Accomplishments

  • Cajun safely completed all 170 drill shaft foundations while matching the client’s quality expectations.

Work Performed

Temporary Case Drill and Pour:

  • 155 EA 30” diam. shafts ranging in depth from 11’–19’
  • 8 EA 36” diam. shafts ranging in depth from 12’–14’
  • 4 EA 48” diam. x 23’ deep drill shafts
  • 3 EA 60” diam. shafts ranging in depth from 20’–24’
  • Installed anchor bolt cages in all drill shafts.

Statistics

  • 3-month duration
  • 2,457 man-hours
  • 16 peak manpower