Cajun Industries was contracted to construct a new 4-story process testing facility within an existing plant, including process, and utility feeds from adjacent units. The project included a new centralized unit pipe rack with an associated pipe rack spur that extends from the central rack to connect the TP’s and OSBL equipment/ buildings to the new process building. OSBL included an analyzer building, RIE/MCC building, a horizontal CO2 Vessel supported at grade, a D.I. water tank supported at grade, multiple smaller equipment and skids supported at grade. A new control room for this unit was established by remodeling the lab area of an existing control room building adjacent to the new facility.
Work Performed
• Installation of ~500 CY
of concrete foundations
and area paving
• Installation of ~200 TNS of new
rack and new process testing
facility structural steel
• Setting of ~90 PCS of
Mechanical Equipmennt
including reactors, scrubbers,
guard bed module, DP tube
bank, hairpin exchangers,
coolers, compressors, pumps,
vessels, and tanks
• Installation of ~14,000’ of process
and utility piping and 13 tie-ins
• Remodel of existing lab area
to create a new control room
• Installation of ~500 CY of concrete
foundations and area paving
• Installation of ~200 TNS of new rack and
new process testing facility structural steel
• Setting of ~90 PCS of Mechanical
Equipmennt including reactors, scrubbers,
guard bed module, DP tube bank, hairpin
exchangers, coolers, compressors, pumps,
vessels, and tanks
• Installation of ~14,000’ of process and
utility piping and 13 tie-ins
• Remodel of existing lab area to create a
new control room