Shell Low Sulfur Gasoline Unit

Client: Shell Refinery

Location: Deer Park, TX

Description: This project involved the erection of all process piping and the installation and alignment of all rotating equipment for a new Low Sulfur Gasoline (LSG) unit. Cajun’s scope included installation of all structured packing (catalyst), Temperature Indicators (TIs), hold-down grids and VEP distributors for tanks and vessels; installation of electrical equipment; installation of underground firewater lines and general site services. Cajun was responsible for Non-Destructive Evaluation (NDE) services including x-ray, hydro-testing, pneumatic testing and post-weld heat treating.

As a result of Cajun’s professionalism and quality workmanship, the client asked that Cajun manage additional work that doubled Cajun’s original contract amount without extending the contract end date. Cajun was able to modify the work plan to complete the work one week ahead of schedule.