Tenaris Bay City Civil Project

Location: Bay City, TX

Description: This project involved construction of a new, seamless tubing manufacturing facility covering approximately 300 acres of developed land. Cajun was responsible for installation of the pipe piles and construction of the spread footing foundations. Cajun worked a 70 hour per week schedule to achieve the aggressive schedule. We installed over 2,280 pipe piles (16″ diameter x 70′ long), placed over 11,700 CY of structural concrete, installed over 1,300 tons of reinforcing steel and placed over 50,000 CY of structural backfill.

Peak manpower for the project was 160. Cajun worked a total of 163,674 man-hours with no OSHA recordable incidents and completed the project two weeks ahead of schedule.